Technical Clarification
Hand Calculation
Technical Clarification Number
HMM02-T-EDG-0066
Guidance
2017-03-23
Where the project team are not able to verify the material thickness as required by the Compliance Guidance, it is acceptable that the project team provide a hand calculation of the material thickness. The project team must provide a confirmation letter within the submission to justify this alternative route as well as a date stamped photograph of the material measured.