Follow

EMI-8 LEGIONELLA

 

Technical Clarification

Legionella and 'Shell & Core' spaces

Technical Clarification Number
EMI8-T-OB1-0712

Guidance
2013-07-22

The following guidance is provided for spaces delivered as ‘Shell & Core’, as defined in the Green Star Office v1 Technical Manual.

Regardless of delivery type (i.e. Conventional, Integrated or Shell & Core), the scope of the credit criteria is applicable to water-based heat rejection system(s) that have been provided serving the building’s nominated area.

 

Credit Interpretation Request

Alternative credit version

Credit Interpretation Request Number
EMI8-C-OB1-0258

Ruling
2011-03-10

Projects registered for Green Star SA Office (Version 1) certification may elect to use the 'Aim of Credit', 'Credit Criteria', 'Documentation Requirements' and 'Additional Guidance' as outlined in the equivalent Emi-8 Legionella credit contained within the Green Star SA Retail Centre (Version 1) Technical Manual, to demonstrate compliance. Where the Green Star SA Retail Centre (Version 1) Emi-8 Legionella credit version is used, Project Teams must clearly indicate the use of this alternative credit version within the submission. For a copy of the Green Star SA Retail Centre (Version 1) Emi-8 Legionella credit, please contact the GBCSA.

 

Technical Clarification

Humidifiers

Technical Clarification Number
EMI8-T-OB1-0259

Guidance
2011-03-10

For the purpose of this credit, humidifiers within HVAC systems are not considered "evaporative cooling systems" or "water based heat rejection systems" and are excluded from the scope of the Credit Criteria.

 

Erratum

Green Star SA - Office v1 Technical Manual: Page 343

Erratum Number
EMI8-E-OB1-0238

Guidance
2011-02-08

Documentation Requirements, documentation table, Design section, delete second bullet point: "Tender drawing(s)."

 

Erratum

Green Star SA - Office v1 Technical Manual: Page 343

Erratum Number
EMI8-E-OB1-0239

Guidance
2011-02-08

Documentation Requirements, documentation table, As Built section, delete second and third bullet points: "As built drawings" and "Extract(s) from the Commissioning Records."

 

Erratum

Green Star SA - Office v1 Technical Manual: Page 343

Erratum Number
EMI8-E-OB1-0240

Guidance
2011-02-08

Documentation Requirements, description of documents, delete the title and description of "Tender drawing(s)", "As built drawing(s)" and "Extract(s) from the Commissioning Records."

 

 

Was this article helpful?