Technical Clarification
Guidance on building services / sub-services included within the scope of Man-02 and Man-03 - UPDATED
Technical Clarification Number
MAN2 -T-OB1-1562
Guidance
2016-08-25
Please refer to the 'Man-02 and Man-03 Supplementary Info Document - UPDATED' attached (below), it shows which services are required to be addressed under both the Man-2 and Man-3 credits, and for Man-2, shows which ASHRAE / CIBSE documents are applicable to each in terms of the credit criteria. Where no suitable ASHRAE / CIBSE document is available, the project team’s ‘Nominated Commissioning’ applies. Please note further guidance on ‘Nominated Commissioning’ is given below the table in the document.
Supplementary Information
See below for attachment.
---------------------------------------------------------------------------------------------------------------------
Credit Interpretation Request
Alternative compliance for MAN 2: CIBSE vs ASHRAE requirements
(SUPERSEDED by MAN2-T-OB1-1562 from 2016-08-25)
Credit Interpretation Request Number
MAN2 -C-OB1-0855
Ruling
2015-01-20
----------------------------------------------------------------------------------------------------------------------
Technical Clarification
Alternative Documentation
Technical Clarification Number
MAN2 -T-OB1-764
Guidance
2014-02-14
This email pertains to the Technical Clarification (TC) submitted for the Man-2 Commissioning and Man-3 Building Tuning credits, seeking approval to submit alternative documentation (extracts from building contracts) for the Man-2 and Man-3 credits in place of ‘Extracts(s) from the Commissioning Specification’ and ‘Extract(s) from the Specification(s)’.
The CIR request is conditionally approved. The approval of this CIR is thus contingent on the following:
All the information required to demonstrate compliance with the credit criteria in both the ‘Extracts(s) from the Commissioning Specification’ and ‘Extract(s) from the Specification(s)’ for Man 2 and Man 3 respectively is included in the proposed alternative documentation (i.e. extracts from the building contract).
Please note that the other documentation requirements stipulated in the Green Star SA – Office v1 Technical Manual must still be adhered to.
Note that this Technical Clarification will be uploaded to the TC, CIR & Errata database available on the GBCSA website.
Technical Clarification
Commissioning reports
Technical Clarification Number
MAN2 -T-OB1-717
Guidance
2013-08-16
The GBCSA notes that there are a number of credits that refer to commissioning reports as a compliance requirement. The GBCSA notes that these credits are not dependent on the Man-2 credit being targeted or achieved. Project teams can still choose whether or not to target the Man-2 credits if the subsequent credits (i.e. ENE-1, ENE-4, Wat-1, Wat-2 and IEQ-1) are targeted. If a project is targeting the Man-2 credit, extracts from the Commissioning Report produced from Man-2 can then be used to demonstrate compliance with the other subsequent credits provided it complies with the documentation requirements for these credits. If the Man-2 credit is not targeted, commissioning for the other credits need to be done in accordance to the stipulated requirements of that particular credit.
----------------------------------------------------------------------------------------------------------------------
Technical Clarification
Commissioning Clauses - lifts and vertical transportation systems
(SUPERSEDED by MAN2-T-OB1-1562 from 2016-08-25)
Technical Clarification Number
MAN2-T-OB1-0370
Guidance
2012-06-13
Technical Clarification
Guidance on building services / sub-services included within the scope of Man-02 and Man-03
(SUPERSEDED by MAN2-T-OB1-1562 from 2016-08-25)
Technical Clarification Number
MAN2 -T-OB1-0430
Guidance
2012-06-13
----------------------------------------------------------------------------------------------------------------------
Technical Clarification
Commissioning Clauses - On site electrical generation systems
(SUPERSEDED by MAN2-T-OB1-1562 from 2016-08-25)
Technical Clarification Number
MAN2-T-OB1-0275
Guidance
2012-06-13
----------------------------------------------------------------------------------------------------------------------
Erratum
Text missing from description of documentation
Erratum Number
MAN2 -E-OB1-509
Guidance
2012-05-22
Documentation Requirements, Description of Documentation, Short report on design intent, add to the second bullet point Building Services, fire protection and hydraulic.
Wherever Building services are mentioned within credit MAN-02, it refers to BMS, mechanical, electrical, HVAC, hydraulic, fire protection and domestic hot water.
----------------------------------------------------------------------------------------------------------------------
Erratum
Green Star SA - Office v1 Technical Manual: Page 9
(SUPERSEDED by MAN2-E-OB1-0509 from 2012-05-22)
Erratum Number
MAN2-E-OB1-0168
Guidance
2012-05-22
----------------------------------------------------------------------------------------------------------------------
Erratum
Green Star SA - Office v1 Technical Manual: Page 11
(UPDATED from 2011-02-08)
Erratum Number
MAN2-E-OB1-0249
Guidance
2012-01-27
Documentation Requirements, description of documents, delete heading and description: "Extract(s) from the Commissioning Records" and "Submitted data must demonstrate … for all other services."
AND;
Documentation Requirements, description of documents, replace "Commissioning Report" with "Extract(s) from Commissioning Report(s)" and insert a fourth bullet point reading: "Reference appended extracts of commissioning records for major plant and equipment (including chillers, boilers, heat pumps, air handling units, water treatment/recycling systems, onsite generation systems, water distribution (chilled, heating hot water and domestic hot and cold water), lighting system, air distribution, lifts and vertical transportation systems and automated controls (within the BMS and/or Energy metering, HVAC, and wet services) as deemed appropriate by the relevant project team members involved in the commissioning process and as referenced in the Commissioning Report."
----------------------------------------------------------------------------------------------------------------------
Technical Clarification
Demonstration of compliance with CIBSE Commissioning codes - Guidance
Technical Clarification Number
MAN2-T-OB1-0227
Guidance
2012-01-06
To provide Project Teams with further guidance regarding the information which would be expected to be included within the Commissioning Records demonstrating the use and adherence to the CIBSE Commissioning Codes, this information as per the Codes may include, but is not limited to the following;
1) Particular and definitive commissioning specifications from the design engineer of each service/discipline setting out clearly what is expected of the commissioning specialist (independent or otherwise). This should include commissioning tolerances on all commissioning parameters and a clear description of how it is intended that the system should operate and the design parameters. The design should also produce ‘cause and effect’ sheets showing how the design is intended to operate. Also, commissioning specification details of safety controls and interlocks to protect the equipment and personnel during the commissioning process;
2) Requirements for witnessing including full details of tolerances applicable to all parameters;
3) Commissioning program including specific period of time for client witnessing;
4) Appropriate health and safety risk assessment and method statements for the tasks to be completed;
5) Commissioning method statement for each system;
6) Pre-commissioning checklists for each system;
7) Commissioning checklists; and,
8) Commissioning certification for each system countersigned by the design engineer, commissioning specialist (independent or otherwise) and the accepting authority (where relevant), and including the record sheets provided in each CIBSE code.
The above items have been determined from a review of the CIBSE Commissioning Codes identifying key issues to be addressed with regards to the correct documentation of a CIBSE Commissioning Code compliant commissioning process of building services. This list is not exhaustive and it is expected that all Project Teams complete their own review of the CIBSE documents and synthesize the important information which they, in their professional opinion and experience, believe are important and represent an improvement from conventional commissioning practices in South Africa and demonstrate the use of the CIBSE Commissioning Codes.
----------------------------------------------------------------------------------------------------------------------
Technical Clarification
Fitout delivery type and scope of Man-2 Commissioning Clauses
Technical Clarification Number
MAN2-T-OB1-0358
Guidance
2012-01-06
Regardless of delivery type (i.e. Conventional, Integrated or Shell & Core), the scope of the Man-2 Commissioning Clauses credit criteria must cover the entire traditional scope of fit-out provided by the base building (i.e. conventional delivery).Therefore, if the design is such that the commissioning of the base build systems will be affected by the tenant works, the scope of the credit criteria extends to full base build final commissioning.
For spaces delivered as ‘Shell & Core’ for a Design rating, it must be clear that the ‘extract(s) from specification’ and ‘confirmation from building owner’ demonstrate the contractual requirement and owner commitment (respectively) for final commissioning of those base build systems that are affected by the tenant works, once the tenant works are completed.
For spaces delivered as ‘Shell & Core’ for an As Built rating, it must be clear that the ‘extract(s) from Commissioning Reports’ demonstrate the base build systems not affected by tenant works have been commissioned (as per the Documentation Requirements) and it is clearly demonstrated through the list of outstanding commissioning issues that final commissioning of those base build systems that are affected by the tenant works will be undertaken, once the tenant works are completed. It is not required that final commissioning of affected base build systems is completed before the Green Star SA submission is completed. It is necessary, however, to clearly demonstrate that the outstanding commissioning issues will be addressed.
----------------------------------------------------------------------------------------------------------------------
Erratum
Green Star SA - Office v1 Technical Manual: Page 10
Erratum Number
MAN2-E-OB1-0248
Guidance
2011-02-08
In Documentation Requirements, Documentation Table, As Built section:
First bullet point, replace "Extract(s) from Commissioning Records" with "Extract(s) from Commissioning Report(s)"
AND;
Delete second bullet point reading: "Commissioning Report"
----------------------------------------------------------------------------------------------------------------------