Follow

ENE-3 LIGHTING POWER DENSITY

 

Erratum

Green Star SA - Office v1 Technical Manual: Page 149 & 150

Erratum Number
ENE3-E-OB1-0440

Guidance
2012-03-14

Documentation Requirements, Documentation Table, As Built section, replace 'Confirmation(s) from the supplier(s)' with 'Confirmation from the contractor'.

AND

Documentation Requirements, Description of documentation, replace 'Confirmation(s) from the supplier(s) of the type and quantity of fittings supplied to the project.' with 'Confirmation from the contractor of the type and quantity of luminaire and lamp types installed in the building.'

 

Erratum

Green Star SA - Office v1 Technical Manual: Page 149

Erratum Number
ENE3-E-OB1-0247

Guidance
2011-08-08

1. Documentation Requirements, documentation table, Design section, delete third bullet point reading "Tender light fittings schedule" and replace with "Tender lighting drawings"

AND;

2. Documentation Requirements, documentation table, As Built Section, delete second bullet reading "As built light fittings schedule" and replace with "As built lighting drawings"

AND;

3. Documentation Requirements, description of documents, delete both lines headed (a) "Extract(s) from the specification(s)..." and (b) "Tender Light Fittings Schedule..." and replace with the following (single) description "Extract(s) from the specification(s) showing the tender light fittings schedule, confirming luminaire and lamp types and quantities."

AND;

4. Documentation Requirements, add new document description reading: "Tender Lighting Drawings indicating the location and area of each typical lighting layout and the luminaries used.

AND;

5. Documentation Requirements, add another new document description reading: "As Built Lighting Drawings indicating the location and area of each typical lighting layout and the luminaries used.

 

Technical Clarification

Integrated fitout

Technical Clarification Number
ENE3-T-OB1-0095

Guidance
2010-08-17

If a project, or part thereof, is delivered as an integrated fitout, it must still be demonstrated that 95% of the Usable Area (UA) meets the credit criteria for the number of points pursued. Meeting rooms, boardrooms and other enclosed spaces which are part of the UA must be included within the area used to demonstrate compliance with the credit criteria. For different spaces with different lighting systems/layouts and therefore different lighting power densities, an area-weighted averaging method, as detailed in the Green Star SA – Office v1 Technical Manual section for this credit, must be used to determine the overall UA compliance with the credit criteria. It is not permissible to exclude areas of the UA on the basis of an integrated fitout.

 

 