Erratum

Green Star SA - Office v1 Technical Manual: Page 224

Erratum Number
MAT2-E-OB1-0333

Guidance
2012-01-17

Documentation Requirements, documentation table, delete bullet point two ‘Site documentation’ in both Design and As Built sections.

AND

Documentation Requirements, documentation table, last bullet point, add after ‘Site documentation’, the following text “OR As built drawing(s) of original building(s)” in both Design and As Built sections.

 

Technical Clarification

Demolition drawings

Technical Clarification Number
MAT2-T-OB1-0312

Guidance
2011-08-22

Demolition drawings may be provided in lieu of As Built Drawings of the Original Buildings, provided that the same information is indicated. If demolition elevations are not available, then floor plans must indicate the locations of reused and demolished facades, which can then be correlated with the tender elevations.

 

Technical Clarification

'Not Applicable' Clause

Technical Clarification Number
MAT2-T-OB1-0042

Guidance
2009-08-20

The Credit Criteria states that if “the total GFA of the original building(s) is less than 20% of the GFA of the new building that replaces it, this credit is ‘Not Applicable.’” The ‘new’ building GFA is considered to be the final GFA of the building, including both the original building GFA and any new GFA added to it through the development.

 

 