Follow

MAT-3 REUSED MATERIALS

Technical Clarification

Quantity surveyor report and short report

Technical Clarification Number
MAT3-T-OB1-0357

Guidance
2012-01-06

This Technical Clarification is applicable to Mat-3 Reused Materials, Mat-6 Steel, Mat-7 PVC Minimisation, Mat-8 Sustainable Timber, Mat-9 Design for Disassembly, Mat-10 Dematerialisation and Mat-11 Local Sourcing.

Where the ‘Documentation Requirements’ (for Design and As Built) request a ‘Short report’ and a ‘Quantity Surveyor report’, if the ‘Short report’ is prepared by the Quantity Surveyor, it is permitted that one consolidated report satisfying both ‘Documentation Requirements’ be submitted instead of two separate documents.

Where the ‘Short report’ is not prepared by the Quantity Surveyor (e.g. green building consultant, Accredited Professional, structural engineer etc.), both the ‘Short report’ and ‘Quantity Surveyor report’ must be submitted independently.

The purpose of the ‘Quantity Surveyor report’ is to validate data (e.g. quantities, costs, Project’s contract value etc.) referenced within the ‘Short report’.

 

Erratum

Green Star SA - Office v1 Technical Manual: Page 227

Erratum Number
MAT3-E-OB1-0244

Guidance
2011-02-08

Documentation Requirements, documentation table, Design AND As Built sections, remove bullet point reading: "Extract(s) from schedule(s)"

 

Erratum

Green Star SA - Office v1 Technical Manual: Page 227

Erratum Number
MAT3-E-OB1-0245

Guidance
2011-02-08

Documentation Requirements, description of documents, delete: "Extract(s) from schedule(s) listing products/materials in the project"

 

Erratum

Green Star SA - Office v1 Technical Manual: Page 228

Erratum Number
MAT3-E-OB1-0192

Guidance
2011-01-06

Documentation Requirements, description of documents, insert at the end of this section "Extract(s) from the issued contract that includes the project's total contract value."

 