Guidance
2014/01/20

On page 304,  Documentation Requirements, description of documents, under ‘Short Report’,  delete the words “and volume” in the 4th bullet point.

 

Erratum

Contractor/supplier short report

Erratum Number
EMI1-E-OB1-745

Guidance
2013-10-15

SUPERCEDED by EMI1-E-OB1-0864

Following on from erratum EMI1-E-OB1-0626 Green Star SA - Office v1 Technical Manual: Page 304, which requires that in the Short report the project references the MASS not Volume of the gas installed. This is also to apply to the contractor/supplier where they are to declare the total gas installed as kg and m3.

 

Technical Clarification

Refrigerant / Gaseous ODP and 'Shell & Core' spaces

Technical Clarification Number
EMI1-T-OB1-0712

Guidance
2013-07-22

The following guidance is provided for spaces delivered as ‘Shell & Core’, as defined in the Green Star SA Office Design v1 Technical Manual.

Regardless of delivery type (i.e. Conventional, Integrated or Shell & Core), the scope of the credit criteria is applicable to all HVAC systems and fire suppression systems provided for the base building.

 

Erratum

Superceded please see EMI1-E-OB1-0864 issued 20-01-2015

Erratum Number
EMI1-E-OB1-0626

Guidance
2013-04-25

 

 

Erratum

Green Star SA - Office v1 Technical Manual: Page 303-305

Erratum Number
EMI1-E-OB1-0399

Guidance
2012-01-26

Documentation Requirements, replace all references of "HVAC systems" with "HVAC systems (including any heat pumps for domestic hot water production)".

AND

Documentation Requirements, description of documentation, under 'Short report' replace "mechanical engineer" with "suitably qualified professional".

 

Technical Clarification

Scope of credit - clarification

Technical Clarification Number
EMI1-T-OB1-0399

Guidance
2012-01-26

For the purposes of this credit, it must be demonstrated that all refrigerants are accounted for including refrigerants within HVAC systems (heating and cooling equipment) and heat-pump systems used for domestic hotwater generation.

 

Erratum

Green Star SA - Office v1 Technical Manual: Page 306

Erratum Number
EMI1-E-OB1-0348

Guidance
2012-01-23

Additional Guidance, Table Emi-1.1, delete "Inergen" and replace with "IG541".

 

Erratum

Green Star SA - Office v1 Technical Manual: Page 304

Erratum Number
EMI1-E-OB1-0234

Guidance
2011-02-08

Documentation Requirements, documentation table, As Built section, second bullet point under heading: "For buildings with refrigerants/gasses:" change "Confirmation from the Contractor/Supplier" to read "Confirmation from the Supplier(s)."

 

Erratum

Green Star SA - Office v1 Technical Manual: Page 305

Erratum Number
EMI1-E-OB1-0235

Guidance
2011-02-08

Documentation Requirements, description of documents, under "Confirmation from the contractor/supplier detailing:" change heading to read "Confirmation from the supplier(s) detailing:" AND; remove two bullet points (and their contents) and replace with: "The HVAC system (and where applicable, the Fire Suppression system) The equipment; the quantity of equipment supplied to the project; the type(s) of refrigerant/gasses used in the equipment; and the total volume of refrigerant/gasses within the equipment."

 

 