Technical Clarification

Demolition drawings

Technical Clarification Number
MAT2-T-RC1-0312

Guidance
2012-07-26

Demolition drawings may be provided in lieu of As Built Drawings of the Original Buildings, provided that the same information is indicated. If demolition elevations are not available, then floor plans must indicate the locations of reused and demolished facades, which can then be correlated with the tender elevations.

 

Erratum

Green Star SA - Retail Centre v1 Technical Manual: Page 236

Erratum Number
MAT2-E-RC1-0333

Guidance
2012-01-17

Documentation Requirements, Documentation Table: delete bullet point two ‘Site documentation’ in both Design and As Built sections.

AND

Documentation Requirements, Documentation Table: last bullet point, add after ‘Site documentation’, the following text “OR As built drawing(s) of original building(s)” in both Design and As Built sections.

 

 