MAT-11 LOCAL SOURCING

 Erratum

Statement of Confirmation 

Technical Clarification Number
MAT11-E-OB1-0919

Guidance
2015-05-26

The documentation requirement 'Statement of Confirmation' can be deleted as a requirement for Design submissions, because at this stage of a project specific material suppliers are often not selected.

Technical Clarification

Point of recovery and manufacture for steel products

Technical Clarification Number
MAT11-T-RC1-0571

Guidance
2012-09-13

For the purpose of Green Star SA the scrap dealer or salvage yard is identified as the location from where the material was salvaged or recovered, the point of recovery. It is not required for the scrap dealer or salvage yard to provide information of where each piece of material which has been purchased from them, has been collected.

The foundry purchasing the salvaged or recovered material from the scrap dealer or salvage yard is considered as the point of manufacture and only that fraction of the material bought from the scrap dealer or salvage yard shall contribute to the value of that material for consideration in the local sourcing credit.

 

Technical Clarification

Calculations - exclusions

Technical Clarification Number
MAT11-T-RC1-0346

Guidance
2012-07-26

As per the MAT-11 Local Sourcing Credit Criteria, “Mechanical, electrical and plumbing components and speciality items such as elevators and equipment are excluded from this credit.” The following components, equipment and speciality items must be excluded from the total contract value calculations for MAT-11 Local Sourcing:

- All Heating, Ventilation and Cooling (HVAC) plant components incl. duct work;
- All Electrical equipment and components incl. light fixtures & fittings and distribution boards;
- All Plumbing system components incl. piping, duct work and sanitary fittings & fixtures
- Lifts;
- Building Management System (BMS) components and;
- Generators.

 

Erratum

Green Star SA - Retail Centre v1 Technical Manual: Page 283-284

Erratum Number
MAT11-E-RC1-0400

Guidance
2012-07-26

Documentation Requirements, documentation table, Design section, replace "Extract from contract" with "Quantity Surveyor report".

AND

Documentation Requirements, description of documentation, replace "Extract(s) from the contract that includes the project's total value." with "Quantity Surveyor report estimating the total material value of the products/materials from within the specified radii as a percentage of the project's total value."

AND

Documentation Requirements, documentation table, As Built section, replace "Extract from contract" with "Statement of confirmation".

AND

Documentation Requirements, description of documentation, add;

"Statement of confirmation from the Contractor, in the form of signed correspondence confirming:
- For all materials and/or products claimed compliant, the manufacturer/supplier of the material/product, the quantity installed within the project; and,
- The material value of compliant materials/products as a percentage of the project's contract value."

 

Technical Clarification

Local Sourcing – Fill material / bulk earthworks

Technical Clarification Number
MAT11-T-RC1-0500

Guidance
2012-05-29

Fill material/bulk earthworks sourced on site, or sourced within close proximity to the site, may contribute to the MAT-11 Local Sourcing credit.
The GBCSA has determined that it is common practice to source a non-neglible proportion of fill material from sources not within close proximity to the project site. Furthermore, bulk earthworks sources are highly variable, depending on project type and building typology. Given this, the inclusion of fill material/bulk earthworks satisfies the intent of the credit criteria and project teams are to be encouraged to source these materials locally.
Additionally, regardless of whether or not the project team has used fill material/bulk earthworks sourced on site or sourced within close proximity of the site, the material cost of the fill material/bulk earthworks must be included in determining the “project’s contract value.”

 

Erratum

Green Star SA - Retail Centre v1 Technical Manual: Page 284

Erratum Number
MAT11-E-RC1-0190

Guidance
2011-01-06

Documentation Requirements, Description of Documents, Short Report: under the first bullet point add "OR For Design projects, list all materials to be sourced locally."

 

Technical Clarification

Mat-11: Short report

Technical Clarification Number
MAT11-T-RC1-0093

Guidance
2010-08-03

For the short report documentation for Design projects, it is not necessary to document all compliant materials' points of origin, extraction and manufacture with distances to site (first bullet point in the Green Star SA - Retail Centre v1 Technical Manual section for this credit). Projects may simply list all materials to be sourced locally.

 

 