Technical Clarification
Signed Statement of Involvement
Technical Clarification Number
MAN1-T-RC1-744
Guidance
2013-10-29
The GBCSA confirm that where an Accredited Professional is not available to complete the 'signed statement of involvement', it is acceptable for this statement to be completed by the AP's manager with the AP's name clearly stated.
The confirmation is still required to confirm that the AP has attended at least 50% of all project design meetings and 75% of all building services meetings.
Comments