Follow

EMI-1 REFRIGERANT/GASEOUS ODP

Erratum

Technical Clarification Number
EMI-1-E-OB1-0864

Guidance
2014/01/20

Documentation Requirements, description of documents, under  ‘Short Report’, delete the words “and mass” in the 4th bullet point

Erratum

Page:338 Retail Technical Manual v1

 

 

Erratum Number
EMI1-E-RC1-0864

Guidance
2015-01-20

Documentation Requirements, description of documents, under ‘Short Report’, delete the words “and mass” in the 4th bullet point.

 

Technical Clarification

Refrigerant / Gaseous ODP and 'Shell & Core' spaces.

Technical Clarification Number
EMI1-T-RC1-0712

Guidance
2013-07-22

The following guidance is provided for spaces delivered as ‘Shell & Core’, as defined in the Green Star SA Retail Centres v1 Technical Manual.

Regardless of delivery type (i.e. Conventional, Integrated or Shell & Core), the scope of the credit criteria is applicable to all HVAC systems and fire suppression systems provided for the base building.

 

Erratum

Green Star SA - Retail Centre v1 Technical Manual: Page 338

Erratum Number
EMI1-E-RC1-0626

Guidance
2013-04-25

‘Documentation Requirements’, ‘Short Report’, in the 4th bullet point, change the word “volume” to read “mass”.

 

Erratum

Green Star SA - Retail Centre v1 Technical Manual: Page 340

Erratum Number
EMI1-E-RC1-0348

Guidance
2012-01-23

Additional Guidance, Table Emi-1.1, delete "Inergen" and replace with "IG541".

 

Erratum

Green Star SA - Retail Centre v1 Technical Manual: Page 338

Erratum Number
EMI1-E-RC1-0236

Guidance
2011-02-08

Documentation Requirements, Documentation Table, As Built section, heading: "For buildings with refrigerants/gasses:" change the third bullet point "Confirmation from the Contractor/Supplier" to read "Confirmation from the Supplier(s)."

 

Erratum

Green Star SA - Retail Centre v1 Technical Manual: Page 339

Erratum Number
EMI1-E-RC1-0237

Guidance
2011-02-08

Documentation Requirements, Description of Documents, Confirmation from the contractor/supplier detailing, change heading to read "Confirmation from the supplier(s) detailing:"

AND

remove two bullet points (and their contents) and replace with: "The HVAC system (and where applicable, the Fire Suppression system) - The equipment; the quantity of equipment supplied to the project; the type(s) of refrigerant/gasses used in the equipment; and the total volume of refrigerant/gasses within the equipment."

 

 

Was this article helpful?