ECO0-T-MR1-0655

Ruling
2013-03-11

If the project is a refurbishment/redevelopment that remains within the existing development footprint (and providing it is outside the required buffers of watercourses), there is no need to include confirmation from a registered ecologist. Confirmation is required and it could simply be included within the Short Report prepared by a suitably qualified professional with reference to supporting evidence (e.g. aerial photos, Google images)

 

 