Follow

MAN-2 COMMISSIONING CLAUSES

Technical Clarification

Guidance on building services / sub-services included within the scope of Man-02 and Man-03 - UPDATED

Technical Clarification Number
MAN2 -T-OB1-1562

Guidance
2016-08-25

Please refer to the 'Man-02 and Man-03 Supplementary Info Document - UPDATED' attached (below), it shows which services are required to be addressed under both the Man-2 and Man-3 credits, and for Man-2, shows which ASHRAE / CIBSE documents are applicable to each in terms of the credit criteria. Where no suitable ASHRAE / CIBSE document is available, the project team’s ‘Nominated Commissioning’ applies. Please note further guidance on ‘Nominated Commissioning’ is given below the table in the document.

Supplementary Information

See below or attachment.

------------------------------------------------------------------------------------------------------------

Technical Clarification

Guidance on building services / sub-services included within the scope of Man-02 and Man-03

(SUPERSEDED by MAN2-T-OB1-1562 from 2016-08-25)

Technical Clarification Number
MAN3-T-OB1-0430

Guidance
2012-06-13

 

Was this article helpful?
0 out of 0 found this helpful
Have more questions? Submit a request

Comments

Powered by Zendesk