What is the relevance of mass for design? Most projects at design don’t have the mass at tender stage

Erratum
EMI1-E-INT1-1452

Guidance
2016/05/26

Underneath Submission Template

INT v1 first bullet reads Providing a tabulated summary of each qualifying equipment within the interior fitout, and the type and mass of refrigerant/gas charge in each;
 remove the words "and mass"

____________________________________________________________

Technical Clarification

What is the relevance of mass for design? Most projects at design don’t have the mass at tender stage

Technical Clarification Number
EMI-1-E-OB1-0864

Guidance
2014/01/20

Superseded by TCE EMI1-E-INT1-1452