ERRATAM
Commissioning data in the Building Operations Manual
MAN3-E-EBP1-1251
Date issued: 21 January 2016
Remove words "atleast 75%" and "by installed kW size" replace with "components of the following systems"
- Commissioning data (for building not older than 5 years). Commission data must cover components of the following systems:
o HVAC system (main plant and air-handling units)
o Water supply system: main pump(s)
----------------------------------------------------------------------------------------
TECHNICAL CLARIFICATION
MAN3-T-EBP1-1188
Date issued: 25 November 2015
Building Operations Manual: ASSET REGISTERS (INFORMATION UP TO SYSTEM LEVEL)
The intent of the Asset Register must be to assist with the management of the building, hence functioning as a record of the maintainable items that is required to be managed by the Facilities/Maintenance team to ensure the premises is managed appropriately.
Technical data provided should assist with:
- Planned maintenance
- Replacement programmes- end of life-cycle
- Sequencing of work
- Management of contractors (SLA’s)
- Parts and materials required
- Maintenance budgets and financial management
The following information will be required all Asset Registers submitted:
- Asset Number
- Asset Name / Description
- Asset Manufacturer
- Asset Serial Number
- Asset Location
- Asset Date of Purchase / Installation date
- Warranty Expiry Date
--------------------------------------------------------------------------------------------------
ERRATUM
Credit Criteria for Building Users' Guide
Erratum Number
MAN3-E-EBP1-1174
Guidance
2015/11/25
1 point is awarded where a simple and easy-to-use Building Users’ Guide has been produced and issued to users, occupants and tenants.
Removed word "automatically" awarded.
Read: If the requirement for a Building Users’ Guide has been satisfied under the Green Star SA Design / As-Built certification, this point will be awarded.
Evidence is required to show the point was awarded for the BUG.
Comments