Follow

General

Credit Interpretation Requests

Where a contractor is not yet employed as project is out on Tender (design submission only)

 Technical Clarification Number

SEC-C-OB1-1409 

Guidance
2016-03-05

The GBCSA confirm for a Design stage project where the contractor has not been appointed  that the Short Report) can be used to demonstrate how the Project Team is using the Tender Specifications to meet the Credit Criteria and to meet the Short Report Design requirements (i.e. where the contractor is required to provide information upfront).

Please note that a ‘Statement of Confirmation’ is not required for submission, where in cases it would be.  

__________________________________________________________________________

Was this article helpful?
0 out of 0 found this helpful
Have more questions? Submit a request

Comments

Powered by Zendesk