MAN-10 BUILDING MANAGEMENT SYSTEMS

 Technical Clarification

Project Specific TC for NA

Technical Clarification Number
MAN10-T-PB1-1475

Guidance
2016-06-28

Where a project has natural ventilation, no vertical transportation, where lights are fitted with on-board/occupancy sensors for control and there are no water heating facilities a project team may submit a project specific CIR for motivation to make this credit NA. 

 

-------------------------------------------------------------------------------------------------------